Description: Install the Overhead Lighting Unit Material List:
Note: With help, lift the
lighting unit into place so it comes down on the back and side walls.
Secure with 8 - #8 screws through countersunk predrilled holes once
you are sure everything lines up and the walls are flush with the
overhead unit. If installed properly, the top - like the base unit,
will have about a 3/4" gap between the wall termination and the
front panel of the top - this is normal, it allows room for the front
panels to be installed later on. Take this time to caulk ALL exposed
edges! the basic structure is done at this point. Take your time to
recheck all your joints. Construction Time : About a half hour
GO TO STEP 6 - INSTALLING THE SHELVING |
All comments and suggestions should be directed to
vze2372e@verizon.net |